Project time tracking template

Log hours by project and task, compare them with the budget and see where time really goes.

Use it on screen
Project time tracking templateProject setupDaily logWeekly reviewProject name and client.📊
How to use itEveryone logs hours against a project and task each day. The project lead compares hours used with the budget each week.

Who uses the project time tracking template and when

Projects run over budget quietly, one extra hour at a time. A shared log of hours by task shows it early, while there is still time to adjust.

Separate billable and non-billable time so both invoicing and internal costs are clear.

14 items. Use it on screen, or print it and fill it in by hand.

Project setup

Daily log

Weekly review

Example budget check

Example budget check
Field What to write
Design Budget 40 h, used 32 h, about 70% done
Build Budget 120 h, used 40 h, about 30% done
Testing Budget 30 h, used 0 h

Putting the project time tracking template to work

  1. Agree task names before starting.
  2. Log daily.
  3. Review weekly with the team.
  4. Raise changes in scope early.
  5. Compare final hours with the estimate for future quotes.

A real-world example

A web agency budgets 40 hours for design. By week 2, 32 hours are used and the work is about 70% done, which points to an overrun of roughly 6 hours. The lead talks to the client about scope before the design phase ends.

Why a project time tracking matters

Tracking hours against a budget by task shows where estimates go wrong while there is still time to act. It also gives a firm basis for change orders and for quoting similar work next time.

Filled-in sample

Project Riverside Library website, client City of Dubuque
Agency Lantern Digital, Dubuque IA
Task Content migration, budget 60 hours
Hours used 45
Percent complete 60%
Projected total 75 hours, 15 over budget
Action Client agreed to cut 40 archive pages; logged Jun 3

At 45 hours and 60% complete, the task projects to 75 hours, which is 15 over budget. The agency raised it with the client and cut scope instead of absorbing the overrun.

Mistakes we see most often

Adjusting the project time tracking for your team

Creative and marketing agenciesSeparate client meetings and revisions from production time, since revisions are where budgets often slip.
Engineering and architecture firmsTrack hours by drawing set or deliverable, which matches how clients approve work.
Quick winKeep the task list short at the start, around five to ten tasks. People log more accurately when the choices are clear.

What people ask about the project time tracking template

Billable vs non-billable?

Billable time is charged to a client; non-billable is internal.

How detailed should tasks be?

Detailed enough to manage, not so detailed that logging is a chore.

Should hours be logged daily?

Yes, memory fades fast.

Can this feed invoices?

Yes, from billable hours times rates.

How do you calculate percent of budget used on a project?

Divide the hours logged so far on a task by its budgeted hours and multiply by 100. Compare that number to the percent of the task that is actually complete. If budget used is well ahead of percent complete, the task is likely to overrun.

How do I estimate a project overrun from tracked hours?

Divide hours used by percent complete to project the total hours the task will take, then subtract the budget. For example, 30 hours at 60% complete projects 50 hours, or 10 over a 40-hour budget. Review it weekly so you can talk to the client before the budget is gone.

Useful next reads

More for the same job

Keep reading