Record a delivery or part that does not meet the specification, and get a corrective action from the supplier.
When a supplier delivers something wrong, the cost lands on you: delays, rework and sometimes a customer complaint. A written report makes the problem specific and measurable.
Track reports by supplier over time. Repeated issues are a reason for a supplier review.
15 items. Use it on screen, or print it and fill it in by hand.
A shop receives 500 brackets; 60 have holes drilled in the wrong position. The 60 are quarantined, the supplier is sent a report with photos, replaces the parts within a week and adds a fixture check to their process.
Quality systems like ISO 9001 expect nonconforming products to be identified, controlled and followed up with corrective action. A written report also supports cost recovery from the supplier and shows patterns when a supplier repeats the same defect.
| Report | NCR-2026-041, Nov 18 |
|---|---|
| Receiving shop | Apex Machining, Wichita KS |
| Supplier and PO | Midwest Castings, PO 7712, line 2 |
| Part and lot | Pump housing PH-220, lot 1036 |
| Finding | Bore diameter 0.004 in over max on 24 of 200 |
| Disposition | 24 returned; 176 accepted after 100% check |
| Corrective action | Tool wear check added; due Dec 5, verify next 3 lots |
The shop checked every remaining part before accepting the rest of the lot, so the disposition is based on measurement, not a sample. Verification is tied to the next three lots so the report closes on evidence.
A product or service that does not meet its requirements.
Receiving inspection or quality.
Your contract decides.
Escalate to a supplier review.
Containment is the immediate step to stop bad parts from being used, like quarantining stock and checking parts already on the line. Corrective action is the supplier’s fix to the root cause so the problem does not come back. A report should record both, and it stays open until the corrective action is shown to work.
Use as is means the nonconforming material will be used without rework, because an engineer or the customer has decided it still works for its purpose. It needs a documented approval with the reason, and in some industries the customer must sign off. It should be rare and never the default.