Inspection and test plan (ITP) template

List every inspection and test for a scope of work, who does it, against what standard and how it is recorded.

Use it on screen
Inspection and test plan…For each activityPointsRecordsActivity or work stage.🧪
How to use itPrepare the ITP before work starts, agree hold and witness points with the client, and record each inspection as the work progresses.

Where the inspection and test plan template fits

An ITP turns quality requirements into a checklist of inspections. It is common in construction, manufacturing and installation work.

Acceptance criteria come from your contract, specifications and applicable standards.

12 items. Fill it in on screen or print a copy.

For each activity

Points

Records

Example row

Example row
Field What to write
Activity Concrete pour, slab
Criteria Rebar spacing and cover per drawing S-201
Point Hold, engineer sign-off
Record Pre-pour inspection form

Putting the inspection and test plan template to work

  1. Build it from the specification.
  2. Agree points with the client.
  3. Brief crews on hold points.
  4. Record results as you go.
  5. Close with all records attached.

How a team used the inspection and test plan

An electrical contractor’s ITP for a new switchboard includes visual inspection on delivery, insulation resistance tests after installation as a witness point, and a hold point before energizing. Each record is filed in the project quality folder.

Why keep an inspection and test plan

An ITP shows the owner, before work starts, how each requirement in the specification will be checked and recorded. It reduces rework by catching failures at the stage they happen, instead of after later work has covered them up.

Sample inspection and test plan, filled in

Project Northgate Water Treatment Plant, Denver CO
Scope Process piping, 6 in stainless lines
Activity Weld visual inspection, 100% of joints
Acceptance criteria Per ASME B31.3, no cracks or undercut beyond limit
Hydrostatic test 1.5x design pressure, 10 min hold, witness point
Hold point No insulation until hydro test signed off
Records Weld map and test report, filed by QC Lisa

The hydro test is a witness point so the client can watch, while the insulation step is a hold point because covering the pipe would hide any leak. Each activity names the standard the inspector will judge against.

Mistakes with the inspection and test plan

When to edit the inspection and test plan

Pipeline and plumbing workAdd pressure test points per section with test duration and pressure readings.
Steel fabricationAdd weld inspection points with inspector qualifications and test methods.
Worth knowingColor-code hold points in red on the plan. Crews see them at a glance on site.

What people ask about the inspection and test plan template

Is an ITP mandatory?

Often required by contracts.

What is a hold point?

Work stops until sign-off.

Who prepares it?

The contractor’s quality lead.

What if a test fails?

Raise a non-conformance report.

What is the difference between a hold point and a witness point in an ITP?

At a hold point, work must stop until the named party has inspected and signed off, so the next stage cannot start without that release. At a witness point, the client or engineer is given notice and may attend, but work can continue if they choose not to come. Mark which one applies to each activity on the plan.

Who prepares an inspection and test plan?

The contractor or subcontractor doing the work usually prepares the ITP, often the quality manager or project engineer, and submits it for client or engineer approval before work begins. It is based on the project specification, drawings and referenced standards. Approved ITPs are revised if the scope or specification changes.

Related resources

More for the same job

More on this topic

Know who worked when

Use the inspection and test plan template for the record you need today. To see who clocked in, and when, book a demo of EZTime.

General information to adapt to your business. Examples on this page are fictional.