A guide to one of the best-known 24/7 shift patterns, with the full cycle, the overtime math and practical tips.
The DuPont schedule is common in operations that never stop: manufacturing plants, utilities, chemical and processing facilities, emergency services, security and some healthcare settings. It is popular because of the long block of seven consecutive days off in every cycle. For an overview of other patterns, see our guide to types of work shifts and the glossary entry on rotating shifts.
Each team works the same sequence, offset by one week from the next team:
| Days | Activity |
|---|---|
| 1–4 | 4 night shifts (12 hours) |
| 5–7 | 3 days off |
| 8–10 | 3 day shifts (12 hours) |
| 11 | 1 day off |
| 12–14 | 3 night shifts |
| 15–17 | 3 days off |
| 18–21 | 4 day shifts |
| 22–28 | 7 days off |
Over 28 days, each employee works 14 shifts of 12 hours, a total of 168 hours, which averages 42 hours per week. With four teams offset by a week, there is always one team on days and one on nights.
Because federal overtime is calculated per workweek, the important question is how the cycle falls into your seven-day workweeks. The weekly hours are very uneven. If the workweek starts on the first night shift of the cycle, the four weeks look like this:
| Workweek | Shifts | Hours | Overtime hours |
|---|---|---|---|
| Week 1 (days 1–7) | 4 | 48 | 8 |
| Week 2 (days 8–14) | 6 | 72 | 32 |
| Week 3 (days 15–21) | 4 | 48 | 8 |
| Week 4 (days 22–28) | 0 | 0 | 0 |
| Total | 14 | 168 | 48 |
Even though the average is 42 hours, this alignment builds in 48 overtime hours per employee every four weeks for non-exempt employees. Other alignments spread the hours differently, but averaging across weeks is never allowed. Your workweek must be fixed and cannot be changed simply to avoid overtime, so model the cost before adopting the pattern. In states with daily overtime, such as California, hours over 8 in a day may also be overtime; see daily overtime rules.
In the alignment above, week 2 contains three day shifts followed, after one day off, by three night shifts. That is a demanding stretch: 72 hours in seven days with a switch from days to nights. Plan it carefully. Make sure the single day off is protected, discourage extra overtime shifts during that week, and give supervisors clear guidance on watching for signs of fatigue. Some organizations adjust the pattern slightly to soften this week, while keeping the long break at the end of the cycle.
With only four teams and 12-hour shifts, one absence leaves a gap that someone has to fill for 12 hours. Common solutions include a small relief crew that works fill-in shifts, cross-trained day workers who can step in, or a rule that vacations are taken during the seven-day break where possible. Avoid relying on people from the team that just finished a night shift, and track how often each employee covers, so extra shifts are shared fairly and overtime stays visible.
| Pattern | Cycle | Notable feature |
|---|---|---|
| DuPont | 28 days | Seven consecutive days off each cycle |
| Pitman (2-2-3) | 14 days | Every other weekend off; see our Pitman schedule guide |
| 4 on, 4 off | 8 days | Simple pattern; days off rotate through the week |
The best pattern depends on your operation, your team’s preferences and local rules.
EZTime scheduling lets you build shifts for each team and repeat them across weeks, while employees see their upcoming shifts in the mobile app. The time clock records actual hours, and overtime alerts help managers see when extra shifts would push someone into additional overtime.
An average of 42 hours per week over the 28-day cycle, though weekly hours vary.
Four teams, to cover 24/7 operations with 12-hour shifts.
Usually yes, for non-exempt employees, in the workweeks where scheduled hours exceed 40.
Fourteen days off in each 28-day cycle, including one block of seven consecutive days.
Not for full 24/7 coverage with 12-hour shifts. Smaller operations often use other patterns, such as fixed day shifts with on-call cover at night.
Many like the long break, but 12-hour shifts and day/night rotation can be tiring. Ask your team before adopting it.
Because EZTime links the schedule to the time clock, you can block early clock-ins or punches outside assigned shifts.